Warning: file_get_contents(/home/httpd/vhosts/ingenta.ch/httpdocs/ingenta-2019/wp-content/plugins/background-image-cropper/background-image-cropper.php): failed to open stream: Permission denied in /home/httpd/vhosts/ingenta.ch/httpdocs/ingenta-2019/wp-includes/functions.php on line 6948 Warning: include_once(/home/httpd/vhosts/ingenta.ch/httpdocs/ingenta-2019/wp-content/plugins/background-image-cropper/background-image-cropper.php): failed to open stream: Permission denied in /home/httpd/vhosts/ingenta.ch/httpdocs/ingenta-2019/wp-settings.php on line 589 Warning: include_once(): Failed opening '/home/httpd/vhosts/ingenta.ch/httpdocs/ingenta-2019/wp-content/plugins/background-image-cropper/background-image-cropper.php' for inclusion (include_path='.:/usr/share/pear:/usr/share/php') in /home/httpd/vhosts/ingenta.ch/httpdocs/ingenta-2019/wp-settings.php on line 589
Der Bau der Brückenfundamente und Widerlagerwände mit den Flügelmauern ist fertiggestellt.
Aktuell werden die Stützmauern hinterfüllt und anschliessend wird der Baugrubenabschluss zurückgebaut. Wegen der engen Platzverhältnisse wurde für das Ziehen der Spundwände teilweise ein 240-Tonnen-Mobilkran eingesetzt.
Nach abgeschlossenem Rückbau der wasserdichten Baugrubenumschliessungen werden die vor den Flügelmauern zu liegen kommenden Ufersicherungen ergänzt und die Baupiste im Flussbereich zurückgebaut.
Danach ist die Brückenbaustelle bereit für den Aufbau des obenliegenden Lehrgerüsts für die Schalung der Brückenplatte.